Project Overview
The Disney Cotino Development in Rancho Mirage, CA is a first-of-its-kind Storyliving by Disney community, designed to combine residential living, recreational amenities, and immersive storytelling. Penta Construction served as the general contractor, and Westcon Construction was awarded critical scopes of structural and site concrete work, including flatwork, foundations, hardscapes, and specialty concrete features.
This high-profile project required precision, craftsmanship, and adherence to strict Disney/DMB Development standards. Westcon contributed to creating durable, functional, and visually striking infrastructure that complements the development's luxury resort-style amenities.
Scope of Work
Westcon's responsibilities on the Cotino Development included:
- Structural Concrete Foundations for community amenity structures.
- Flatwork & Hardscape including pedestrian walkways, patios, pool decks, and gathering areas.
- Decorative Concrete Elements integrated into high-visibility areas adjacent to water features.
- Site Development Support including grading, formwork, and specialty pours coordinated with landscaping and amenity installation.
The service agreement scope also included Parkview Substation Foundations, requiring three (3) PT support pier foundations with anchor bolts, testing, and reporting.
Key Challenges & Solutions
1. High-Profile Standards
Disney projects demand strict quality control and aesthetic precision. Westcon implemented enhanced QA/QC measures and worked closely with inspectors to ensure all finishes met both technical and design expectations.
2. Complex Coordination
With multiple trades working simultaneously in amenity areas, Westcon adjusted work sequencing to ensure smooth coordination with landscape, pool, and utility crews. This minimized delays and kept the project aligned with Penta's overall schedule.
3. Water-Adjacent Construction
Many concrete elements were placed adjacent to the lagoon and pool features. Special attention was given to formwork, mix designs, and curing methods to ensure long-term durability in high-moisture conditions.
Visual Progression

Amenity Building Foundations & Flatwork – Early structural concrete placement for community buildings by the lagoon.

Patio & Hardscape Work – Crews finishing flatwork at shaded amenity areas.

Roadway & Infrastructure Grading – Large-scale grading and prep for site flatwork.

Recreation & Gathering Areas – Installation of concrete pathways and hardscapes around pickleball courts.

Lagoon-Side Construction – Forming and pouring decorative concrete elements along the shoreline.

Pool Deck & Amenity Zone – Crews delivering large-scale flatwork for the lagoon-side pool area.

Final Hardscape Connections – Walkways and plaza areas tying together multiple amenities.

Wide Aerial of Completed Scope – Aerial view of lagoon, amenities, and surrounding site with Westcon’s completed concrete work.
Results & Impact
- Delivered structural and site concrete scope on time to support Penta's phased delivery schedule.
- Achieved Disney-quality standards, ensuring long-term performance and aesthetics.
- Successfully coordinated with multiple trades in high-traffic amenity zones.
- Contributed to a landmark project that will be a model for future Storyliving by Disney communities.
Conclusion
The Disney Cotino Development highlights Westcon's capability to deliver high-profile, detail-driven concrete scopes within large-scale master-planned communities. Our work with Penta Construction and DMB Development reinforced Westcon's reputation for quality, reliability, and adaptability, ensuring this landmark project meets the expectations of Disney, residents, and visitors alike.
 
 