Project Case Study
West Coast Self Storage -- Indio, CA
Client: Consolidated Contracting Services, Inc.
Subcontractor: Westcon Construction Services, Inc.
Project Overview
The West Coast Self Storage project in Indio, CA was developed to provide a modern, secure, and efficient storage facility for the growing Coachella Valley community. Westcon Construction was selected by Consolidated Contracting Services, Inc. as the subcontractor responsible for the structural and site concrete scopes of work, delivering high-quality craftsmanship under a fixed-price subcontract.
Our team performed extensive structural concrete foundations, site paving, sidewalks, curbs, gutters, ADA-compliant ramps, and off-site improvements, all in strict compliance with project specifications and local agency standards.
Contract Information:
- Project: 44-513 West Coast Self Storage, NWB Indio
- Owner: NWB Indio LLC
- General Contractor: Consolidated Contracting Services, Inc.
- Subcontractor: Westcon Construction Services, Inc.
- Scope of Work: Structural Concrete & Site Concrete
Scope of Work
Westcon's responsibilities included:
- Structural Concrete Foundations for storage building slabs, piers, and footings.
- Site Concrete & Hardscape including curbs, gutters, sidewalks, cross gutters, and drive approaches.
- ADA Accessibility Features such as handicap ramps with tactile warning systems.
- Off-Site Improvements at Vecino Way and Calhoun Street, including demolition, re-grading, and reconstruction of curb & gutter, sidewalks, and cross gutters.
- Project Enhancements requested through field work orders and change orders, such as installation of bollards, added base material at crossings, and blockouts for RV parking structures.
Key Challenges & Solutions
1. Scope Adjustments
Several out-of-scope modifications were required during construction, including added bollards, off-site concrete rework, and blockouts for RV parking structures. Westcon's team collaborated closely with the GC and inspector to quickly address these adjustments while minimizing delays.
2. Off-Site Coordination
IID utility work required reconstruction of off-site sidewalks, curbs, and gutters. Westcon managed multiple mobilizations and traffic control coordination, completing the improvements without impacting adjacent properties.
3. Quality & Compliance
All structural concrete was placed with 4,000 PSI mix design, achieving 75--80% strength within 7 days as required. Westcon also ensured ADA accessibility compliance across all ramps and sidewalks.
Visual Progression







Results & Impact
- Delivered structural and site concrete scope on time and within budget.
- Successfully managed multiple change orders without schedule impact.
- Achieved high-quality finishes across structural slabs, site paving, and ADA features.
- Supported Consolidated Contracting's delivery of a state-of-the-art storage facility to the Indio community.
Conclusion
The West Coast Self Storage project demonstrates Westcon's expertise in structural concrete and site improvement projects, our ability to adapt to changing project needs, and our commitment to delivering quality work that meets client and community expectations.
Through close coordination with Consolidated Contracting, inspectors, and local agencies, Westcon successfully completed a complex scope of work that enhances the long-term durability, functionality, and accessibility of this new facility in Indio, CA.
 
 